What a unit price analysis (APU) is
A unit price analysis (APU, from the Spanish análisis de precios unitarios) is the calculation that explains what it costs to carry out one unit of an activity: a square meter of wall, a cubic meter of concrete, a linear meter of pipe. It breaks that cost down into what is actually consumed (materials, labor, equipment and transport) and shows every quantity and every price.
It is the foundation of the budget. The project budget is the sum, over all activities, of the quantity of work times the unit price, and every unit price comes from an APU.
The four blocks of an APU
Materials
Quantity times unit price for each input. If you apply a waste percentage, write it down: it is the figure that causes the most arguments when someone reviews the analysis.
Labor
Daily wage times productivity rate, that is, the fraction of a day's wage that the crew spends per unit of the activity. The daily wage must include the benefits your company pays: otherwise the cost comes out short.
Equipment and tools
Equipment rate times the time used per unit. Small tools are usually calculated as a percentage of labor; the analyst sets the percentage.
Transport
Volume times distance times rate, when the input has to be brought to the site and transport is not included in its price.
Worked example: one square meter of block wall
| Line | Subtotal |
|---|---|
| Clay block | COP 27,500 |
| Bedding mortar (m³) | COP 13,500 |
| Skilled mason (daily wage) | COP 10,800 |
| Helper (daily wage) | COP 7,200 |
| Mixer (per day) | COP 600 |
| Item | Amount |
|---|---|
| Materials | COP 41,000 |
| Labor | COP 18,000 |
| Equipment and tools | COP 600 |
| Small tools (5% of labor) | COP 900 |
| Direct cost | COP 60,500 |
| Item | Amount |
|---|---|
| Administration | COP 6,050 |
| Contingencies | COP 3,025 |
| Profit | COP 3,025 |
| VAT on the profit | COP 575 |
| Unit price | COP 73,175 |
How to review an APU someone hands you
- Recalculate every subtotal: quantity times price. A subtotal that does not add up is the first thing that should show up.
- Add up the blocks and compare with the declared direct cost.
- Check where each price comes from: date, supplier, city. A price with no origin cannot be defended.
- Compare the productivity rates with the reality of your own project, not with someone else's table.
- Confirm that the units match: m, m², m³, kg.
Limits of this guide
It explains the method and shows an example with invented figures. It does not provide market prices or reference productivity rates, and it does not set AIU percentages. The example assumes a single activity with no adjustments for height, weather or location.
Frequently asked questions
Is an APU the same as a budget?
No. The APU calculates the price of one unit of an activity; the budget multiplies that price by the quantity of work and adds up all the activities.
Where does AIU come in?
After the direct cost. There is an AIU calculator on this site; it explains how the VAT is calculated and does not state any percentage.
How often should an APU be updated?
When input prices or daily wages change. If you sign long contracts, it is wise to write down which index you use for price adjustment.
Which productivity rates should I use?
The ones you measure on your own project or on similar projects of yours. Other people's tables work as a starting point, not as backing.
Sources
- This guide describes a general-purpose method and does not depend on a standard or on external data. The figures in the example are calculated by Renka's APU engine with invented prices.