What the AIU calculates
In a construction contract in Colombia, the price is commonly agreed as the direct cost plus a percentage for administration, one for contingencies (imprevistos) and one for profit (utilidad): hence AIU, from Administración, Imprevistos, Utilidad. This calculator takes the direct cost and those three percentages and returns each item in Colombian pesos, the subtotal before VAT, the VAT and the total.
It does not decide which percentages to use. Your tender documents, your contract and your cost analysis define them; the tool only does the arithmetic without mistakes and leaves it in plain view.
Method: the formula step by step
Each item is rounded to the cent before it is added, as you would do in a spreadsheet with the rounding function in every cell.
The VAT base rule is the one most often confused: VAT is not computed on the whole subtotal but on the fees the contract agrees or, if none were agreed, on the profit. The source is at the bottom of this page; confirm with your accountant how it applies to your contract.
Worked example
A direct cost of COP 100,000,000 with administration 10%, contingencies 5%, profit 5% and VAT 19% gives the following. The figures are computed by the tool's own code.
| Item | Value |
|---|---|
| Direct cost | COP 100,000,000 |
| Administration (10%) | COP 10,000,000 |
| Contingencies (5%) | COP 5,000,000 |
| Profit (5%) | COP 5,000,000 |
| Subtotal before VAT | COP 120,000,000 |
| VAT base (the profit) | COP 5,000,000 |
| VAT (19%) | COP 950,000 |
| Total | COP 120,950,000 |
If the same contract agrees fees of 8% of the direct cost, the VAT base becomes COP 8,000,000, the VAT COP 1,520,000 and the total COP 121,520,000. The subtotal before VAT does not change (COP 120,000,000): only what is taxed changes.
And if the profit were 8% instead of 5%: the subtotal rises to COP 123,000,000, the VAT to COP 1,520,000 and the total to COP 124,520,000. Moving the profit moves the subtotal and also the VAT base, so it is worth trying your real figures in the tool before closing a bid.
Assumptions of the tool
- The direct cost already includes everything direct (materials, labor, equipment, transport). The APU guide explains how it is built.
- The three percentages apply to the direct cost, not one on top of another.
- You type the VAT rate; the tool does not choose it for you.
- Everything is in Colombian pesos, rounded to the cent at each item.
- Calculations run in your browser: what you type is not sent to any server.
Limits: what this tool does not do
- It does not state a minimum, maximum or "correct" percentage of administration, contingencies or profit: sector sources disagree and each contract rules.
- It is not tax advice. The VAT treatment depends on the type of contract and on who contracts; if your case is special (for example, a contract with a public entity), confirm it with your accountant.
- It does not check that your percentages are reasonable for the market; only that they are between 0 and 100%.
- The contract must say which part corresponds to fees or profit: the tool assumes you already did that.
Frequently asked questions
Which AIU percentage should I use?
None that we can state. Your tender documents or contract and your construction cost analysis define it. You will find different figures in different sector sources; that is why the tool leaves the three fields in your hands and its initial values are only an example.
Is VAT computed on the whole AIU?
No, according to the rule cited at the bottom: the base is the agreed fees or, if none were agreed, the profit. The tool calculates it that way. If your contract or your accountant use another base, the result changes: check it with them.
Is AIU the same as APU?
No. The APU (análisis de precios unitarios, the unit-price breakdown) builds the direct cost of each activity; the AIU is added afterwards, on the total direct cost. There is a guide with a worked APU.
Is the data I type saved?
No. The calculation runs in your browser and is not sent to any server.
Does it work for Mexico or the United States?
Each country builds the price differently. There is a calculator for Mexico (precio unitario) and another for the United States (overhead and profit).