What it calculates
In Mexican public works, the unit price (precio unitario) of a work item (concepto de trabajo) is built from five components: direct costs, indirect costs (costos indirectos), financing cost (costo por financiamiento), the contractor's profit (utilidad) and additional charges (cargos adicionales). This calculator applies the five in that order, each on what has accumulated before, and adds VAT (IVA) at the end.
You enter the percentage of each component: they depend on your analysis and on the bases of the tender (licitación) or the contract.
Method: the formula step by step
The cumulative order is the calculation convention this tool implements. If your tender bases ask for another order or other application bases, the result will not match: your tender document rules.
Worked example
| Component | Value |
|---|---|
| Direct cost | MX$1,000,000.00 |
| Indirect costs (12%, on the direct cost) | MX$120,000.00 |
| Financing (1%, on direct + indirects) | MX$11,200.00 |
| Profit (10%, on the accumulated amount) | MX$113,120.00 |
| Additional charges (0.5%, on the accumulated amount) | MX$6,221.60 |
| Unit price before VAT | MX$1,250,541.60 |
| VAT (16%) | MX$200,086.66 |
| Total | MX$1,450,628.26 |
Assumptions and limits
- Each component is calculated on what has accumulated up to the previous one; the additional charges, on everything before them.
- You type the VAT rate: it can vary by zone or by the regime of the work.
- It does not state "correct" percentages for indirects, financing or profit.
- It does not replace the unit price analysis of the tender or the judgment of whoever signs the proposal.
- Calculation in your browser: nothing you type is sent.
Frequently asked questions
Which indirects and profit percentages should I enter?
Those from your analysis and those your tender bases allow. The tool's initial values are an example so the arithmetic reads clearly; they are not a recommendation.
Which components make up the unit price?
According to article 185 of the regulation cited below: direct costs, indirects, financing, the contractor's profit and additional charges.
What if my tender calculates it another way?
Then your tender rules. This tool helps you understand the order and check a calculation; it does not replace the document that governs your contract.