Free tool

Overhead and profit: from direct cost to price (US)

Short answer

In US construction estimating it is common to add overhead and profit to the direct cost. This calculator applies overhead on the direct cost and profit on direct plus overhead, and treats sales tax on materials as a contractor cost. It is not a legal formula: your contract rules.

Updated October 23, 2026 · Published by Renka Consulting

Example values: replace them with your contract's.

Direct cost
$100,000.00
Sales tax on materials
$2,900.00
Overhead
$10,290.00
Profit
$11,319.00
Price
$124,509.00
Total
$124,509.00

What it calculates

In construction estimating in the United States it is common to build the price as direct cost plus overhead (general expenses) plus profit. This calculator applies the overhead on the direct cost and the profit on direct plus overhead, and lets you include the sales tax on materials as a contractor cost.

There is no single legal formula: it is an estimating convention, and what your contract or your company says rules. You enter the percentages.

Method: the formula step by step

Sales tax on materials = materials × state rate Base = direct cost + sales tax on materials Overhead = base × overhead % Profit = (base + overhead) × profit % Price = base + overhead + profit

The sales tax on the materials the contractor buys enters the cost before the markup; that is why the tool does not add it at the end as a tax charged to the client. The rate depends on the state and you enter it.

Worked example

Direct cost of 100,000 US dollars, 40,000 of it in materials
ItemValue
Direct cost (includes the materials)$100,000.00
Sales tax on materials (7.25% of 40,000)$2,900.00
Overhead (10%)$10,290.00
Profit (10%)$11,319.00
Price$124,509.00

Figures computed by the tool's own code. The 7.25% rate is an example value, not your state's.

Assumptions and limits

  • Overhead is applied on the direct cost including sales tax; profit, on that total plus the overhead.
  • Some companies calculate profit on the direct cost alone or use another base: if yours is different, the result will not match.
  • It does not include local taxes, bonding, insurance or permits if they are not in your direct cost.
  • It does not state "correct" percentages of overhead or profit.
  • Calculation in your browser: nothing you type is sent.

Frequently asked questions

How much overhead and profit should I enter?

Whatever comes out of your office costs and your bidding strategy. The tool's initial values are illustrative.

Why isn't the sales tax added at the end?

Because the contractor pays the sales tax on the materials when buying them: it is their cost, and it enters the base on which overhead and profit are applied.

Is it an official formula?

No. It is an estimating convention; your contract or your client's rules govern.